Pleasant Hill North Main Street Reconstruction

Project Data
Client:  Village of Pleasant Hill
Completion Date: 2014
Cost: $1,500,000
$   975,000  OPWC Grant
$    175,000  ODOT Grant
$   400,000 Local Funding
Contact Information:
Village of Pleasant Hill
8 West High Street
Pleasant Hill, OH  45359

Village of Pleasant Hill hired our team from Access Engineering Solutions to design and execute the reconstruction of North Main Street.

Included in the project were new storm sewer, catch basins, curb and gutter, sidewalks, pavement and miscellaneous other improvements.

Our involvement in the project also covered assisting the village in obtaining the necessary funding, design, permits, bidding, construction administration and other required tasks.